Owner: City of Bloomington
Completion: 2009
Project Description:
3D Design Studio was asked to update
Bloomingtons Parks Master Plan. The process began with an Inventory of
each of the parks, an assessment of user needs resulting in meetings
with all schools, youth sports organizations and City departments. A
list of City wide Recommendations were prepared, combined with
park-by-park recommendations. Next we developed a listing of Priorities
and each came with a budget range of costs for each project. Costs were
projected through 5 years to create the new Master Plan.